scott_hancock-urmc.rochester
-
8/2/2012 9:32:03 AM
Scheduled Synchronization Not Synchronizing All Tasks
Hi,
I have the Content Synchronization task set to run using the Windows service. The Content Synchronization task to run once a day, every day at 2 A.M. When I check the Staging Tasks list in CMS Desk it still shows tasks from the day before that were not synchronized and their result is blank (not failed). For example yesterday we created a bunch of users, the synchronization ran at 2am today but the users were not synchronized. I then ran the synchronization from CMS desk and all the users synchronized except for one that failed. There are no exceptions in the log. I have debugging turned on for the Scheduled tasks but I don't see where I can view that information. There are no other processes running at the same time.
Do you have any suggestions on how I can debug this? Is there a way to create a log of the scheduled tasks?
I'm running v6.0.40 (SP1).
Thanks, Scott
|